Related Topics:
Facility ID: 44004DTRXC1100N
Facility Name and Address: DETREX 1100 STATE RD ASHTABULA, OH 44004 Parent Company: DETREX CORP Industry: Other Basic Inorganic Chemical Manufacturing (325180) Chemical: Zinc compounds Reports: View TRI Facility profile report for this facility View TRI Form R submissions by this facility |
|
*You can navigate within the map with your mouse. |
Production Related Waste Management for Selected Chemical
lchemid=N982
Chart Options1: |
Waste Management Comparison -
Display facility comparison report for this industry and chemical
Display facility comparison report for this parent company
Pollution Prevention Activities for Selected Chemical
Reporting Year | Section 8.10: Newly Implemented Source Reduction Activity | Section 8.10: Methods to Identify Activity | Section 8.11: Optional Pollution Prevention Information* |
---|---|---|---|
2019 |
Barriers: B7-Barriers to P2 B7 - No known substitutes or alternative technologies.
|
Barriers to P2: B7 - No known substitutes or alternative technologies. - Zinc Oxide is needed for use in our products for the zinc content. |
|
2016 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T04: Participative team management
|
|
2015 |
Barriers: B7-Barriers to P2 B7 - No known substitutes or alternative technologies.
|
Other Environmental Practices - Waste reduction and pollution prevention activities include but are not limited to research and development efforts for process improvements and control, production planning, proper inventory management techniques, process improvement meetings with total employee involvement to eliminate manufacturing of off specification materials, and predictive maintenance along with preventive maintenance. We are also ISO 14001 and ISO 9001 certified and have a mercury PMP program in place. Both ISO 14001 and ISO 9001 drive our waste reduction and pollution prevention activities.
Barriers to P2: B7 - No known substitutes or alternative technologies. - Best available technology is currently being used to reduce emissions. |
|
2014 |
Source Reduction: Methods for Identifying Pollution Prevention Opportunities - Waste reduction and pollution prevention activities include but are not limited to research and development efforts for process improvements and control, production planning, proper inventory management techniques, process improvement meetings with total employee involvement to eliminate manufacturing of off specification materials, and predictive maintenance along with preventive maintenance. We are also ISO 14001 and ISO 9001 certified, and have a mercury PMP program in place. Both ISO 14001 and ISO 9001 drive our waste reduction and pollution prevention activities. |
||
2013 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management |
|
2012 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management |
Source Reduction - Waste reduction and pollution prevention activities include but are not limited to research and development efforts for process improvements and control, improving production planning, proper inventory management techniques, process improvement meetings with all employees involved to eliminate manufacturing of off specification materials, and preventive maintenance and predictive maintenance. We are also ISO 14001 certified, ISO 9001 certified, and have a mercury PMP program. Both ISO 14001 and ISO 9001 drive our efforts for continuous improvements in day to day activities for waste reduction and pollution prevention. |
2011 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management |
Source Reduction - Waste reduction and pollution prevention activities include but are not limited to research and development efforts for process improvements and control, improving production planning, proper inventory management techniques, process improvement meetings with all employees involved to eliminate manufacturing of off specidication materials, and preventive maintenance and predictive maintenance. We are also ISO 14001 certified, ISO 9001 certified, and have a mercury PMP program. Both ISO 14001 and ISO 9001 drive our efforts for continuous improvements in day to day activities for waste reduction and pollution prevention. |
2010 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management |
Source Reduction - Waste reduction and pollution prevention activities include but are not limited to research and development efforts for process improvements and control, improving production planning, proper inventory management techniques, process improvement meetings with all employee involvement to eliminate manufacturing of off specification materials, and preventive maintenance and predictive maintenance. We are also ISO 14001 certified, ISO 9001 certified, and have a mercury PMP program. Both ISO 14001 and ISO 9001 drive our efforts for continuous improvements in day to day activites for waste reduction and pollution prevention. |
2009 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management |
Source Reduction - Waste reduction and pollution prevention activities include but are not limited to research and development efforts for process improvements and control, improving production planning, proper inventory managemnt techniques, process improvemnt meetings with all employee involvement to eliminate manufacturing of off specification materials, and preventive maintenance and predictive maintenance. We are also ISO 14001 certified and ISO 9001 certified, and have a mercury PMP program. Both ISO 14001 and ISO 9001 drive our efforts for continuous improvemnts in day to day activities for waste reduction and pollution prevention. |
2008 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W29: Other changes in inventory control Source Reduction:: W42: Substituted raw materials |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T11: Other |
Source Reduction - Waste reduction and pollution prevention activities include but are not limited to research and development efforts for process improvements and control, improving production planning, proper inventory managment techniques, process improvement meetings with all employee involvement to eliminate manufacturing of off specification materials, and preventive maintenance. We are also ISO 14001 certified, ISO 9001 certified, and have a mercury pmp program. Both ISO 14001 and ISO 9001 drive our effort for continuous improvement in day to day activities for waste reduction and pollution prevention. |
2007 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W29: Other changes in inventory control Source Reduction:: W42: Substituted raw materials |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T11: Other |
Source Reduction - Waste reduction and pollution prevention activities include but are not limited to research and development efforts for process improvements and control, improving production planning, proper inventory managment techniques, process improvement meetings with all employee involvement to eliminate manufacturing of off specification materials, and preventive maintenance. We are also ISO 14001 certified, ISO 9001 certified, and have a mercury pmp program. Both ISO 14001 and ISO 9001 drive our effort for continuous improvement in day to day activities for waste reduction and pollution prevention. |
2006 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W29: Other changes in inventory control Source Reduction:: W42: Substituted raw materials |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T11: Other |
|
2005 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W29: Other changes in inventory control |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) |
|
2004 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W29: Other changes in inventory control |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) |
|
2003 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W29: Other changes in inventory control |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) |
|
2002 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W29: Other changes in inventory control |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) |
|
2001 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W29: Other changes in inventory control |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) |
|
2000 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W29: Other changes in inventory control |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) |
|
1999 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W29: Other changes in inventory control |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) |
|
1998 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W29: Other changes in inventory control |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) |