Production Related Waste Management for Selected Chemical
lchemid=0000079107
Chart Options1: |
Waste Management Comparison -
Display facility comparison report for this industry and chemical
Display facility comparison report for this parent company
Pollution Prevention Activities for Selected Chemical
Reporting Year | Section 8.10: Newly Implemented Source Reduction Activity | Section 8.10: Methods to Identify Activity | Section 8.11: Optional Pollution Prevention Information* |
---|---|---|---|
2020 |
Source Reduction:: W19: Other changes in operating practices
|
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T11: Other Barriers: B8-Barriers to P2 B8 - A reduction does not appear to be technically feasible |
Barriers to P2: B8 - A reduction does not appear to be technically feasible - Destruction is 99.9%; At the present time, 100% destruction is not technically feasible. |
2019 |
Source Reduction:: W19: Other changes in operating practices
|
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program)
|
W19: Installed vapor recovery on tanker loading of finished goods, removing a source of fugitive emissions |
2016 |
Barriers: B6-Barriers to P2 B6 - Pollution prevention previously implemented - additional reduction does not appear technically or economically feas
Barriers: B1-Barriers to P2 B1 - Insufficient capital to install new source reduction equipment or implement new source reduction activities/initiat |
Barriers to P2: B1 - Insufficient capital to install new source reduction equipment or implement new source reduction activities/initiat - Bulk storage has been investigated and would reduce waste from drum packaging, but is cost prohibitive at this time Barriers to P2: B6 - Pollution prevention previously implemented - additional reduction does not appear technically or economically feas - Previously implemented quality assurance/improvement activities have reduced releases to the extent practicable |
|
2015 |
Barriers: B7-Barriers to P2 B7 - No known substitutes or alternative technologies.
|
Barriers to P2: B7 - No known substitutes or alternative technologies. - Substance is a primary raw material in finished product Other Environmental Practices: Energy Recovery - Initiated zero-landfill project to remove production-related wastes from landfill disposal |
|
2013 |
Other Barriers to Source Reduction - Finished Good properties prohibit substitution of raw materials |
||
2012 | Other Environmental Practices - The site continues to maximize reuse of off-spec finished goods and to recycle raw materials where possible, resulting in lower waste generation | ||
2009 | Source Reduction - Facility continues to focus on waste reduction by standardizing waste-generation processes and improving quality processes, resulting in overall waste reduction of 10%/year |