Related Topics:
Facility ID: 45050FTPRD300LA
Facility Name and Address: GLASS COATINGS & CONCEPTS 300 LAWTON AVE MONROE, OH 45050 Parent Company: Industry: Paint and Coating Manufacturing (325510) Chemical: Zinc compounds Reports: View TRI Facility profile report for this facility View TRI Form R submissions by this facility |
|
*You can navigate within the map with your mouse. |
Production Related Waste Management for Selected Chemical
lchemid=N982
Chart Options1: |
Waste Management Comparison -
Display facility comparison report for this industry and chemical
Pollution Prevention Activities for Selected Chemical
Reporting Year | Section 8.10: Newly Implemented Source Reduction Activity | Section 8.10: Methods to Identify Activity | Section 8.11: Optional Pollution Prevention Information* |
---|---|---|---|
2019 |
Other Environmental Practices: General Environmental Management - General Environmental Controls and Practices previously implemented. Source Reduction: Ways P2 Was Incorporated in Original Process Design - P2 barriers: Pollution prevention previously implemented - additional reduction does not appear technically or economically feasible. |
||
2013 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
2012 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
2011 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
2010 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
2009 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
2008 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
2007 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
2006 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
2005 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
2004 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |