Related Topics:
Facility ID: 52809GHRML7001B
Facility Name and Address: PB LEINER USA 7001 BRADY ST DAVENPORT, IA 52806 Parent Company: TESSENDERLO USA INC Industry: All Other Basic Organic Chemical Manufacturing (325199) Chemical: Ammonia Reports: View TRI Facility profile report for this facility View TRI Form R submissions by this facility |
|
*You can navigate within the map with your mouse. |
Production Related Waste Management for Selected Chemical
lchemid=0007664417
Chart Options1: |
Waste Management Comparison -
Display facility comparison report for this industry and chemical
Display facility comparison report for this parent company
Pollution Prevention Activities for Selected Chemical
Reporting Year | Section 8.10: Newly Implemented Source Reduction Activity | Section 8.10: Methods to Identify Activity | Section 8.11: Optional Pollution Prevention Information* |
---|---|---|---|
2022 |
Source Reduction:: S04: Substituted manufacturing aid, processing aid, or other ancillary chemical
|
Methods to Identify SR Opportunities: T04: Participative team management
Barriers: B1-Barriers to P2 B1 - Insufficient capital to install new source reduction equipment or implement new source reduction activities/initiat |
S04: Review of possible replacement of ammonia system with a glycol system. Barriers to P2: B1 - Insufficient capital to install new source reduction equipment or implement new source reduction activities/initiat - Capital costs to replace ammonia system with a glycol system are too great. |
2021 |
Source Reduction:: S04: Substituted manufacturing aid, processing aid, or other ancillary chemical[-100%]
|
Methods to Identify SR Opportunities: T11: Other
|
S04: Substituted aqueous ammonia for caustic soda in the process. Source Reduction - Substituted aqueous ammonia for caustic soda in the process. |
2020 |
Barriers: B1-Barriers to P2 B1 - Insufficient capital to install new source reduction equipment or implement new source reduction activities/initiat
|
Barriers to P2: B1 - Insufficient capital to install new source reduction equipment or implement new source reduction activities/initiat - Cost of replacing anhydrous ammonia with glycol system too great. |
|
2019 |
Barriers: B1-Barriers to P2 B1 - Insufficient capital to install new source reduction equipment or implement new source reduction activities/initiat
|
Barriers to P2: B1 - Insufficient capital to install new source reduction equipment or implement new source reduction activities/initiat - Cost of replacing anhydrous ammonia with glycol system too great. |
|
2016 |
Barriers: B1-Barriers to P2 B1 - Insufficient capital to install new source reduction equipment or implement new source reduction activities/initiat
|
Barriers to P2: B1 - Insufficient capital to install new source reduction equipment or implement new source reduction activities/initiat - Concern over cost of using a different material for cooling units in refrigeration area (ie glycol). |
|
2014 |
Other Environmental Practices: General Environmental Management - Project underway to replace old piping in order to prevent possible leak in the future. |
||
2012 | Source Reduction - The reduction in ammonia release can be attributed to continued vigilance on the ammonia pumping system through maintenance. | ||
1995 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W35: Installed vapor recovery systems Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program)
Methods to Identify SR Opportunities: T10: Vendor assistance Methods to Identify SR Opportunities: T10: Vendor assistance Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T10: Vendor assistance |
|
1994 |
Source Reduction:: W52: Modified equipment, layout, or piping
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
|
|
1993 |
Source Reduction:: W52: Modified equipment, layout, or piping
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T04: Participative team management |
|
1992 |
Source Reduction:: W52: Modified equipment, layout, or piping
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T04: Participative team management |
|
1991 |
Source Reduction:: W52: Modified equipment, layout, or piping
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T04: Participative team management |