Facility Name and Address: 409 - REDWING OILSEEDS PLANT 118 MAIN ST RED WING, MN 55066 Parent Company: ARCHER DANIELS MIDLAND CO Industry: Soybean and Other Oilseed Processing (311224) Chemical: n-Hexane Reports: View TRI Facility profile report for this facility View TRI Form R submissions by this facility |
|
*You can navigate within the map with your mouse. |
Production Related Waste Management for Selected Chemical
lchemid=0000110543
Chart Options1: |
Waste Management Comparison -
Display facility comparison report for this industry and chemical
Display facility comparison report for this parent company
Pollution Prevention Activities for Selected Chemical
Reporting Year | Section 8.10: Newly Implemented Source Reduction Activity | Section 8.10: Methods to Identify Activity | Section 8.11: Optional Pollution Prevention Information* |
---|---|---|---|
2021 |
Source Reduction:: S41: Improved scheduling, record keeping, or procedures for operations, cleaning, and maintenance
|
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) |
Source Reduction - Red Wing uses a focused improvement style to reduce usage of TRI chemical Source Reduction - PSM program invites hourly employees as voice of expert to optimize process |
2020 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) |
W13: Control of shutdown and startups prevents excessive hexane loss Source Reduction - PSM and Focused Improvement groups involve operators in reduction of hexane usage Source Reduction - PSM and Focused Improvement groups involve operators in reduction of hexane usage |
2019 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) |
|
2018 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) |
W13: Red Wing takes advantage of planned downtime to address and preventive maintenance or proactive maintenance activites. Source Reduction - Same PSM program as above Source Reduction - Employee participation in Process Safety Management of Highly Hazardous Chemical, employee input is encouraged and incorporated into source reduction activities. |
2017 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) |
|
2016 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures[-0-4%]
|
Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program)
Methods to Identify SR Opportunities: T04: Participative team management |
W13: Improved preventative and predictive maintenance practices Source Reduction - During Quarterly PSM meetings, hourly and supervisory staff work together to improve process and reduction of chemical usage. Source Reduction - Feedback from employees during Quarterly PSM meetings. |
2015 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures[-0-4%]
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers[-5-14%] Source Reduction:: W52: Modified equipment, layout, or piping[-5-14%] |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T11: Other Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) |
|
2014 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures[-0-4%]
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers[-5-14%] Source Reduction:: W52: Modified equipment, layout, or piping[-5-14%] |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T11: Other Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) |
W13: Increased preventative maintenance activities on pump seals, converting to double mechanical type seals prevents leaks in system. W52: Increased preventative maintenance activities on pump seals, processing piping and equipment. Source Reduction - Quarterly Process Safety Management meetings provides input to process improvement. Source Reduction - Under PSM, employees provide input to process. |
2013 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T11: Other Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) |
Source Reduction - Recommendations of efficiencies during process safety management meetings. |
2012 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
|
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T11: Other |
Source Reduction - Management tries to minimize unplanned shutdowns and keep oilseed production steady; all of which can influence chemical usage rates. Source Reduction - Depending upon market availability of oilseeds, production rates are increased or decreased to keep equipment in operation and eliminate TRI chemical from being lost in production process. |
2001 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
|
|
2000 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) |
|
1999 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) |
|
1998 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) |
|
1997 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) |
|
1996 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) |
|
1995 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
|