Facility Name and Address: LOVELAND PRODUCTS INC-BILLINGS (FORMERLY TRANSBAS) 1525 LOCKWOOD RD BILLINGS, MT 59101 Parent Company: AGRIUM INC Industry: Pesticide and Other Agricultural Chemical Manufacturing (325320) Chemical: Methoxone Reports: View TRI Facility profile report for this facility View TRI Form R submissions by this facility |
|
*You can navigate within the map with your mouse. |
Production Related Waste Management for Selected Chemical
lchemid=0000094746
Chart Options1: |
Waste Management Comparison -
Display facility comparison report for this industry and chemical
Display facility comparison report for this parent company
Pollution Prevention Activities for Selected Chemical
Reporting Year | Section 8.10: Newly Implemented Source Reduction Activity | Section 8.10: Methods to Identify Activity | Section 8.11: Optional Pollution Prevention Information* |
---|---|---|---|
2017 |
Barriers: B6-Barriers to P2 B6 - Pollution prevention previously implemented - additional reduction does not appear technically or economically feas
|
Barriers to P2: B6 - Pollution prevention previously implemented - additional reduction does not appear technically or economically feas - Past efforts of recycling, dust collection and where possible dedication of equipment have been successfully implemented. Recycling is done under close scrutiny to avoid cross contamination or generating additional off spec material (resulting in waste). Any additional dedication of equipment would limit profitability. Other Environmental Practices: Recycling - Recycle rinses in production when ever possible Source Reduction: Source Reduction - Dust control, scheduling efficiencies |
|
2016 |
Barriers: B6-Barriers to P2 B6 - Pollution prevention previously implemented - additional reduction does not appear technically or economically feas
|
Barriers to P2: B6 - Pollution prevention previously implemented - additional reduction does not appear technically or economically feas - Recycling and scheduling long runs are currently in place. Formulation of this ingredient continued to reduce in 2016. |
|
2015 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W29: Other changes in inventory control |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T11: Other |
Source Reduction - Reduced product mix which not only reduced the quantity of this material used but also decreased the number of cleanouts, waste and the water treatment of streams with this constituent to virtually nothing. Source Reduction - Employees at all levels seek ways to minimize change overs and cleanouts which create waste. Other Environmental Practices: Source Reduction - Dedication of byproducts from other streams which allows for more recycling in compatible products. Other Environmental Practices: Waste Treatment - Dedication of byproduct streams and improved preventative maintenance has reduced the amount of this material from the water stream that is treated. In 2015 this constituent did not enter the water treatment stream. Other Environmental Practices: Recycling - Dedication of byproducts from other streams which allows for more recycling in compatible products. |
2014 |
Source Reduction:: W49: Other raw material modifications
|
Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program)
|
Source Reduction - Segregated MCPA byproduct streams to recycle in compatible products while maintaining product integrity. Other Environmental Practices: Recycling - Recycling is part of the culture of the facility and goes beyond regulated materials. Facility management includes recycling in production planning efforts, reports recycling achievements/opportunities to employees to maintain buy in and tracks recycling initiatives as a part of corporate sustainability goals. |
2013 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W33: Installed overflow alarms or automatic shutoff valves |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) Methods to Identify SR Opportunities: T10: Vendor assistance Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) Methods to Identify SR Opportunities: T10: Vendor assistance |
|
2012 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W33: Installed overflow alarms or automatic shutoff valves |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) Methods to Identify SR Opportunities: T10: Vendor assistance Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) Methods to Identify SR Opportunities: T10: Vendor assistance |
W14: Long runs of compatible products were scheduled to minimize waste and maximize recycling. W19: In 2012 LPI installed an automated control system that opened and closed valves, transferred materials, turn on and off agitators and pumps and set off overflow alarms. W33: In 2012 LPI installed an automated control system that opened and closed valves, transferred materials, turn on and off agitators and pumps and set off overflow alarms. Source Reduction - The vendor worked closely with operators and maintenance to develop checklists, perform maintenance and address concerns. Source Reduction - Employees were included throughout the installation of the automation system. Source Reduction - A management of change and process hazard analysis were performed prior and during the installation of the auto system. Employees involved in the process, representing various levels and disciplines and the vendor were included in these reviews |
2011 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W68: Improved rinse equipment operation |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) |
|
2010 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W68: Improved rinse equipment operation |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) |
|
2009 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W68: Improved rinse equipment operation |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program) |
|
2008 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |
|
2007 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |
|
2006 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W19: Other changes in operating practices Source Reduction:: W32: Improved procedures for loading, unloading, and transfer operations |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management |
|
2005 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W29: Other changes in inventory control |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |
|
2002 |
Source Reduction:: W19: Other changes in operating practices
Source Reduction:: W21: Instituted procedures to ensure that materials do not stay in inventory beyond |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
2001 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W58: Other process modifications |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |
|
2000 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W58: Other process modifications |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |
|
1999 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W58: Other process modifications |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |
|
1998 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W58: Other process modifications |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |
|
1997 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W58: Other process modifications |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |
|
1996 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W58: Other process modifications |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |
|
1995 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W58: Other process modifications |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |