Related Topics:
Facility ID: 01453NVCRC31FUL
Facility Name and Address: TEKNOR APEX ELASTOMERS INC. 33 FULLER ST LEOMINSTER, MA 01453 Parent Company: TEKNOR APEX CO Industry: All Other Rubber Product Manufacturing (326299) Chemical: Zinc compounds Reports: View TRI Facility profile report for this facility View TRI Form R submissions by this facility |
|
*You can navigate within the map with your mouse. |
Production Related Waste Management for Selected Chemical
lchemid=N982
Chart Options1: |
Waste Management Comparison -
Display facility comparison report for this industry and chemical
Display facility comparison report for this parent company
Pollution Prevention Activities for Selected Chemical
Reporting Year | Section 8.10: Newly Implemented Source Reduction Activity | Section 8.10: Methods to Identify Activity | Section 8.11: Optional Pollution Prevention Information* |
---|---|---|---|
2020 |
Source Reduction:: W19: Other changes in operating practices[-5-14%]
|
Methods to Identify SR Opportunities: T04: Participative team management
Barriers: B7-Barriers to P2 B7 - No known substitutes or alternative technologies. |
Source Reduction - To reduce quantity of errors in add making process Barriers to P2: B7 - No known substitutes or alternative technologies. - Two cure technologies available....... phenolic (using zinc based materials) & organic peroxide based. Results in differing properties. Customer specified cure technologies used. Not optional. |
2019 |
Source Reduction:: W52: Modified equipment, layout, or piping
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Barriers: B2-No Information B2 - Require technical information on pollution prevention techniques applicable to specific production processes. |
W52: Modified loss-in-weight feeders with pipe-in-pipe and flexible rubber boot system to keep transferred material contained Source Reduction - Upgraded dust collection equipment |
2017 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures[-0-4%]
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers[-0-4%] |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T04: Participative team management |
|
2016 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures[-0-4%]
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers[-0-4%] |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T11: Other Methods to Identify SR Opportunities: T03: Materials balance audits |
W13: Established preventive maintenance program W14: Modified additive blend volumes / production throughput schedules to avoid residual additive blends at end of runs |
2015 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W32: Improved procedures for loading, unloading, and transfer operations Source Reduction:: W39: Other spill or leak prevention |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T10: Vendor assistance Methods to Identify SR Opportunities: T11: Other Methods to Identify SR Opportunities: T04: Participative team management |
|
2014 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices Source Reduction:: W32: Improved procedures for loading, unloading, and transfer operations Source Reduction:: W58: Other process modifications |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T11: Other Methods to Identify SR Opportunities: T04: Participative team management |
|
2013 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W36: Implemented inspection or monitoring program of potential spill or leak sources Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T10: Vendor assistance |
|
2012 |
Source Reduction:: W52: Modified equipment, layout, or piping
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T04: Participative team management |
|
2011 |
Source Reduction:: W52: Modified equipment, layout, or piping
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T04: Participative team management |
|
2010 | Source Reduction - Significant efforts made in dust control systems, procedures, and housekeeping practices to minimize releasable zinc compound particulates. |