Facility ID: 52627DPNTF80135
Facility Name and Address: AXALTA COATING SYSTEMS USA LLC- FORT MADISON PLANT 803 35TH ST FORT MADISON, IA 52627 Parent Company: AXALTA COATING SYSTEMS LLC Industry: Plastics Material and Resin Manufacturing (325211) Chemical: Butyl acrylate |
|
Reporting Year | Section 8.10: Newly Implemented Source Reduction Activity | Section 8.10: Methods to Identify Activity | Section 8.11: Optional Pollution Prevention Information* |
---|---|---|---|
2023 |
Source Reduction:: S42: Changed production schedule to minimize equipment and material changeovers
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
|
S42: We've attempted to reduce cleanings as much as possible |
2020 |
Source Reduction:: W71: Other cleaning and degreasing modifications
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Barriers: B1-Barriers to P2 B1 - Insufficient capital to install new source reduction equipment or implement new source reduction activities/initiat |
W71: fewer washes between batches Barriers to P2: B1 - Insufficient capital to install new source reduction equipment or implement new source reduction activities/initiat - COVID19 |
2019 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
|
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program)
|
|
2018 |
Source Reduction:: W52: Modified equipment, layout, or piping
|
Methods to Identify SR Opportunities: T04: Participative team management
|
|
2017 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
|
W14: batches are campaigned to reduce washes |
2016 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
|
W14: Batches are campaigned to reduce clean up and tank usage |
2015 |
Source Reduction:: W32: Improved procedures for loading, unloading, and transfer operations
|
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
|
|
2014 |
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
|
Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program)
|
Source Reduction - Production analyzed all the materials made and created a new schedule to reduce the amount of cleans and/or boils between batches. All the cleans and boils go to waste and therefore this has reduced our waste greatly. |
2013 |
Source Reduction:: W52: Modified equipment, layout, or piping
|
Methods to Identify SR Opportunities: T04: Participative team management
|
|
2012 |
Source Reduction:: W52: Modified equipment, layout, or piping
|
Methods to Identify SR Opportunities: T04: Participative team management
|
|
2011 |
Source Reduction:: W52: Modified equipment, layout, or piping
|
Methods to Identify SR Opportunities: T04: Participative team management
|
|
2010 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T11: Other
|
|
2009 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T11: Other
|
|
2008 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T11: Other
|
|
2007 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T11: Other
|
|
2006 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T11: Other
|
|
2005 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T11: Other
|
|
2004 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T11: Other
|
|
2003 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T11: Other
|
|
2002 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W39: Other spill or leak prevention Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits |
|
2001 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W39: Other spill or leak prevention Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits |
|
2000 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W39: Other spill or leak prevention Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits |
|
1999 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W39: Other spill or leak prevention Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits |
|
1998 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W39: Other spill or leak prevention Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits |
|
1997 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W39: Other spill or leak prevention Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits |
|
1996 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W39: Other spill or leak prevention Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits |
|
1995 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W39: Other spill or leak prevention Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits |
|
1994 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W39: Other spill or leak prevention Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits |
|
1993 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W39: Other spill or leak prevention Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits |
|
1992 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W39: Other spill or leak prevention Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits |
|
1991 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W39: Other spill or leak prevention Source Reduction:: W52: Modified equipment, layout, or piping |
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T02: External pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T03: Materials balance audits |
The Waste Management Hierarchy |
The waste management hierarchy established by the Pollution Prevention Act (PPA) guides waste generators toward the best options for managing wastes.
The preferred option is to prevent pollution at its source, but for waste that is generated, the preferred management methods are recycling, followed
by burning for energy recovery, treatment and, as a last resort, disposing of the waste.
|