TRI Pollution Prevention Report for AACRON INC and Nitric acid

Facility ID: 55447CRNNC2705C

Facility Name and Address:
AACRON INC
2705 CHESHIRE LN
PLYMOUTH, MN 55447

Parent Company: CROWN EXTRUSIONS

Industry: Electroplating, Plating, Polishing, Anodizing, and Coloring (332813)
Chemical: Nitric acid

Production Related Waste Management for Selected Chemical


lchemid=007697372
    Waste Management Comparison - 2019



Pollution Prevention Activities for Selected Chemical


Reporting Year Section 8.10: Newly Implemented Source Reduction Activity Section 8.10: Methods to Identify Activity Section 8.11: Optional Pollution Prevention Information*
2022 Source Reduction:: S41: Improved scheduling, record keeping, or procedures for operations, cleaning, and maintenance
Methods to Identify SR Opportunities: T04: Participative team management
2021 Source Reduction:: S41: Improved scheduling, record keeping, or procedures for operations, cleaning, and maintenance
Methods to Identify SR Opportunities: T04: Participative team management
2020 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Methods to Identify SR Opportunities: T04: Participative team management
2019 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Methods to Identify SR Opportunities: T04: Participative team management
2018 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Methods to Identify SR Opportunities: T04: Participative team management
2017 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Methods to Identify SR Opportunities: T04: Participative team management
2016 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Methods to Identify SR Opportunities: T04: Participative team management
2015 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s)
Methods to Identify SR Opportunities: T04: Participative team management
2014 Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Methods to Identify SR Opportunities: T04: Participative team management
W14: We tried to keep our production scheduled for brite dip Minimized so we do not have to have the tank on all the time, reducing the amount of nictric we use, But our customer log demanded that we keep it on longer hrs to keep up with the demand.

2013 Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W64: Improved draining procedures
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management
2012 Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W64: Improved draining procedures
Source Reduction:: W84: Developed a new chemical product to replace previous chemical product
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T10: Vendor assistance
W84: W43 We Changed or deoxidizer to a sulfuric base and eliminated the nitric in that process.Now the only nitric comes from the britedip process

2011 Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W64: Improved draining procedures

Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T10: Vendor assistance
2010 Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W64: Improved draining procedures
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management
2009 Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W65: Redesigned parts racks to reduce dragout

Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program)
2008 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures

Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers

Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program)
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program)
2007 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures

Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program)
Methods to Identify SR Opportunities: T04: Participative team management
2006 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management
2005 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management
2004 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W65: Redesigned parts racks to reduce dragout
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program)
2003 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W65: Redesigned parts racks to reduce dragout

Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program)
2002 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management
2001 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures

Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program)
Methods to Identify SR Opportunities: T04: Participative team management
2000 Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W19: Other changes in operating practices
Methods to Identify SR Opportunities: T10: Vendor assistance
Methods to Identify SR Opportunities: T04: Participative team management
1999 Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Methods to Identify SR Opportunities: T10: Vendor assistance
1998 Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers
Source Reduction:: W54: Instituted better controls on operating bulk containers to minimize discarding
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T10: Vendor assistance
1997 Source Reduction:: W24: Instituted better labeling procedures
Source Reduction:: W33: Installed overflow alarms or automatic shutoff valves
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program)
1996 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Methods to Identify SR Opportunities: T05: Employee recommendation (independent of a formal company program)
1995 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W52: Modified equipment, layout, or piping

Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T09: Trade association/industry technical assistance program
1994 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Methods to Identify SR Opportunities: T11: Other
1993 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Methods to Identify SR Opportunities: T11: Other
1992 Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Methods to Identify SR Opportunities: T11: Other
*Classifications of Optional Pollution Prevention Information shown in brackets are provided by EPA.


TRI Pollution Prevention Glossary

The Waste Management Hierarchy

The waste management hierarchy established by the Pollution Prevention Act (PPA) guides waste generators toward the best options for managing wastes. The preferred option is to prevent pollution at its source, but for waste that is generated, the preferred management methods are recycling, followed by burning for energy recovery, treatment and, as a last resort, disposing of the waste.
  • Source Reduction includes activities that eliminate or reduce the generation of chemical waste.
  • Recycling includes the recovery of a toxic chemical in waste for reuse.
  • Energy Recovery includes the combustion of toxic chemicals in waste to generate heat or electricity.
  • Treatment includes the destruction of a toxic chemical in waste.
  • Disposal or Other Releases includes toxic chemical quantities entering the environment.
The PPA requires facilities to provide the following details about each chemical they report to TRI: