Facility ID: 59101TRNSB1525L
Facility Name and Address: LOVELAND PRODUCTS INC-BILLINGS (FORMERLY TRANSBAS) 1525 LOCKWOOD RD BILLINGS, MT 59101 Parent Company: AGRIUM INC Industry: Pesticide and Other Agricultural Chemical Manufacturing (325320) Chemical: Dimethylamine |
|
Reporting Year | Section 8.10: Newly Implemented Source Reduction Activity | Section 8.10: Methods to Identify Activity | Section 8.11: Optional Pollution Prevention Information* |
---|---|---|---|
2015 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
|
Methods to Identify SR Opportunities: T04: Participative team management
|
Source Reduction - Reduced product mix and improved scheduling of production runs. |
2014 |
Barriers: B6-Barriers to P2 B6 - Pollution prevention previously implemented - additional reduction does not appear technically or economically feas
|
Barriers to P2: B6 - Pollution prevention previously implemented - additional reduction does not appear technically or economically feas - This material has been evaluated extensively thru multiple process hazard analysis. The use of this material is monitored closely to minimize emission and safety concerns. |
|
2013 |
Source Reduction:: W19: Other changes in operating practices
|
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) Methods to Identify SR Opportunities: T10: Vendor assistance |
|
2012 |
Source Reduction:: W19: Other changes in operating practices
|
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) Methods to Identify SR Opportunities: T10: Vendor assistance |
W19: Installation of automative control system to open and close valves, turn on pumps and monitor transfer of materials. Source Reduction - A process hazard analysis was conducted to review safe operations as well as environmental, safety and operations concerns. The PHA team included employees in the process, employees at all levels and pertainent disciplines and the vendor. Source Reduction - The vendor worked closely with operators and maintenance to develop checklists, perform maintenance and address concerns. Source Reduction - The management of change and process hazard analysis require employees working in the process as well as other related process' be included. |
2011 |
Source Reduction:: W19: Other changes in operating practices
|
Methods to Identify SR Opportunities: T04: Participative team management
|
|
2008 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |
|
2007 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |
|
2006 |
Source Reduction:: W19: Other changes in operating practices
Source Reduction:: W31: Improved storage or stacking procedures Source Reduction:: W32: Improved procedures for loading, unloading, and transfer operations Source Reduction:: W49: Other raw material modifications |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T03: Materials balance audits Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T01: Internal pollution prevention opportunity audit(s) Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management |
|
2005 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W14: Changed production schedule to minimize equipment and feedstock changeovers Source Reduction:: W29: Other changes in inventory control Source Reduction:: W32: Improved procedures for loading, unloading, and transfer operations |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T04: Participative team management Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) |
|
2002 |
Source Reduction:: W19: Other changes in operating practices
|
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T06: Employee recommendation (under a formal company program) |
|
2001 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
2000 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
1999 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
1998 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
1997 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
|
1996 |
Source Reduction:: W13: Improved maintenance scheduling, recordkeeping, or procedures
Source Reduction:: W19: Other changes in operating practices |
Methods to Identify SR Opportunities: T04: Participative team management
Methods to Identify SR Opportunities: T04: Participative team management |
The Waste Management Hierarchy |
The waste management hierarchy established by the Pollution Prevention Act (PPA) guides waste generators toward the best options for managing wastes.
The preferred option is to prevent pollution at its source, but for waste that is generated, the preferred management methods are recycling, followed
by burning for energy recovery, treatment and, as a last resort, disposing of the waste.
|